Please follow all local safety standards


This method of procedure has been created to assist all installers in setting the Ginlong Solis Inverters to comply with Rule 21 Phase 1 July 26th changes. This change can only be completed on all Ginlong Solis Rule 21 compliant inverters. For any questions please contact our service line at 866-438-8408.


Step 1: Turn the inverter on with DC Voltage Only


Step 2: Go to the Advanced Settings in the Menu


Step 3: Grid On/OFF and set Grid to OFF


Step 4: Go to STD. Mode Settings


Step 5: Go to Working Mode Set


Step 7 Single Phase: Set the settings as follows:

  • V1 – 220
  • V2 – 232
  • V3 – 247
  • V4 – 256
  • Q1 – 30% - Default
  • Q2 – 30% - Default

Step 7 Three Phase: Set the settings as follows:

  • V1 – 255
  • V2 – 268
  • V3 – 286
  • V4 – 297
  • Q1 – 30% - Default
  • Q2 – 30% - Default


Step 8: Hit Escape


Step 9: Save and Send


Step 10: Go to Grid On/OFF and turn the grid back on.


Step 11: Complete your commissioning process.